|
No one tool is perfect for every application.
In the world of trenchless installation, many contractors who
are accustomed to performing larger bores with augers have discovered
the advantages of using pipe rammers in assisting or completing
problem or difficult bores.
Although
pipe rammers have been widely used in Europe for decades, awareness
and use of the trenchless tool has only recently gained wider
acceptance in North America. Contractors working in the most
difficult soil conditions were the first to be attracted to
the idea of incorporating as pipe rammer with their fleet of
augers. By focusing on the bottom line of efficiently completing
bores, these innovative contractors have positively positioned
themselves in their perspective markets.
One contractor in particular, Frank
Helm of Helm & Sons, Salt Lake City, UT, was one of the
first to combine pipe rammers with augers on a consistent basis.
His success and failures formed the benchmark upon which other
contractors base their opinion of this unconventional arrangement.
For Helm, it wasn't an "either or"
proposition. His successful business already owned several augers,
but there were job-site circumstances that warranted an investment
in pipe ramming. Helm's crews often encountered soil conditions
where augers were not efficient or effective. These soils generally
had a high content of rock and cobble.
Instead of displacing soil, pipe
rammers simply insert casings into the ground. It's the same
basic premise as sticking a drinking straw into a chocolate
chip shake. At this point, there is substance both inside and
outside the straw, or pipe. Removing the "spoils" from inside
the pipe casing can be accomplished in two ways. In smaller
diameter pipe, spoils are ejected by using compressed air. Augers
are also used to remove the earth and rock which was "swallowed"
from the inside of larger diameter casings.
Following are the stories of three
contractors who recently combined the two trenchless boring
tools to creatively overcome obstacles and successfully accomplish
difficult bores.
Location:
Boise, ID
Contractor:
North American Construction, Inc.
Objective:
Install sewer pipe beneath irrigation canal
Jack Seburn of North American Construction
(NAC), based in Caldwell, ID, recently combined augers and rammers
for positive results on a sanitary sewer installation in Boise,
ID.
The City of Boise required that a
section of sewer pipe be installed beneath an irrigation canal.
The job was open to both auger drilling and open cut methods,
although the latter was deemed highly undesirable.
The complexity of boring through
the rock soil was made worse by the project specification that
the bore be made at a 10 percent grade. By offering the auger
method, Seburn was successful in providing the lowest bid. Unfortunately,
the bid was still too high for the city to afford.
This bid rejection caused Seburn
to consider alternatives. He recalled stories about other trenchless
methods of performing bores. As he consulted friends in the
construction industry, he learned about the trenchless construction
method of pipe ramming.
The Trenchless Technology Center
in Ruston, LA, provided Seburn with the name of several contractors
who incorporate pipe ramming, including Frank Helm of Salt Lake
City and Jim Bradshaw of Omaha. After his conversations with
Helm and Bradshaw, he quickly realized that pipe ramming was
the answer to his dilemma. Bradshaw told him of successful pipe
ramming jobs in similar and worse soil conditions than what
Seburn would encounter in Boise. Bradshaw also indicated that
he economy of using ramming tools helped him secure several
jobs.
Seburn
was then put in touch with Mike Schwager, Rammer Product Specialist
for TT Technologies, Inc. After some discussion and consideration,
they were able to formulate a game plan.
The job involved the ramming of 200
feet of 24-inch pipe at a 10 percent uphill grade beneath the
canal. This pipe would be traveling through glacial till with
rock diameters of 12 inches. The 24-inch pipe would simply "swallow-up"
the rock and soil that was in its path. To help accomplish this
task, the first pipe section is fitted with a "cutting shoe."
This beveled edge of the shoe allows the pipe to slice through
the soil more efficiently. Once a section or two of pipe was
installed, crews would then turn to the auger to remove the
spoils from inside the casing.
Arrangements had been made with Schwager,
as well as Jim Moore from TT Technologies to bring a Koloss
Pipe Rammer, along with the appropriate accessories. Mark Hanson
of Idaho Bit and Steel also lent his expertise to the project.
By arranging to have a rammer on
a rental basis, Seburn was then able to re-estimate the installation,
resulting in NAC being awarded the bid. "Originally, some of
the municipality's specs wouldn't have allowed us to using ramming.
But I worked with Masco (Boise, ID), the general contractor,
and we were able to get a few changes made," said Seburn.
At the job site, the pipe was positioned
on two 24-inch pipe cradles atop the auger track. The 0 to 40-foot
lead pipe was rammed into the rocky soil in just 20 minutes.
The lead pipe fit-up weld was made and the next section of pipe
(40 to 80 feet) was also rammed in just 20 minutes.
At this point, it was decided that
crews would auger-out the pipe and check the grade. Crews used
a laser to ascertain the angle. It was determined that the grade
had dropped only two inches in 80 feet, which was well within
the pre-established tolerances.
The final two 40-foot sections were
then installed, taking just under an hour ramming time for each
pipe. The entire installation took place over four days, with
just three hours of total ramming time. Referring to the general
contractor and municipality's reaction to the installation,
Seburn remarked, "They were pleased, happy with the time frame."
NAC then purchased a Grundoram from
TT Technologies and have used it at several job sites.
Reflecting on the Boise job, Seburn
said, "Augers could have created voids. That would have been
a problem for this installation beneath the canal. The really
good thing about the ramming tool is that it eliminated the
risk of voids."
Location:
Brookfield, WI
Contractor:
Michels Pipeline Construction, Inc.
Objective:
Install casings beneath railway
What do difficult soil conditions,
a high water table, exact grade requirements and sub-zero temperatures
have in common? They were all present at a pipe ramming job
in Wisconsin.
Michels Pipeline of Brownsville,
WI, had the task of installing 180 feet of 48-inch steel casings
beneath two railroad tracks near Brookfield, WI. It had been
determined that the traditional method of augering would not
be a good choice because of the high water table and mixed glacial
till soil. In fact, boulders ranging from 16 to 20 inches in
diameter peppered the earth.
Michels Pipeline's Field Superintendent
Bill Weltin and staff then considered using a pipe rammer to
effect the installation. They contacted TT's Schwager and Rich
Prosser for suggestions.
For this installation, a Grundoram Goliath pipe rammer was selected for the 48-inch casing installation.
The Goliath has a diameter of 18 inches with air consumption
of 1,225 cfm. "In this area of the country, because of glacial
till, the use of ramming is appropriate," said Weltin.
Once Super Excavators (Milwaukee,
WI), the primary contractor, finished setting the bore shaft
and de-watering the site, the Michels' crews could proceed with
the installation in sub-zero cold.
Schwager helped with fabrication
of a "cutting shoe," which was welded to the front of the initial
casing to facilitate slicing larger diameter than the casing,
a minimal void was created, usually resulting in a drop of four
to 5 inches for every 100 feet of installation.
Only seven feet of the casing was
rammed the first day, due to the exact requirement of the bore
trajectory. The condition of soft sand in the shoring box also
allowed some settling of the tool which slowed efforts.
The next morning, the first section
was finished and the second section of casing was welded to
the back of it. In less than an hour, the second section was
in. The inside of the first two casings were then augered out
to remove spoils. This eliminated internal friction, which sped
the subsequent installations. It also allowed crews to check
the grade.
It was found that the leading pipe
edge had dropped 2 1/2 inches in 40 feet. To help maintain a
workable grade, Michels crews installed two concrete wings beneath
the pipe by cutting from inside the casing.
It helped. Grade loss was maintained
at a consistent level. Each pipe section installation was accomplished
in under one hour. The entire casing installation was completed
in less than 30 days from the first day of ramming. "It (rammer)
successfully brought the casing across," said Weltin.
In all, the grade had dropped a total
of 10 1/2 inches in 180 feet, which was deemed workable by the
contractor and municipality. After spoils were removed with
an auger, a new 24-inch PVC sewer pipe was secured inside the
180 feet of casing.
Location:
Bricktown, NJ
Contractor: Northeast
Construction
Objective:
Install pipe beneath four-lane highway
Yet another scenario where a pipe
rammer and auger worked successfully together took place recently
in New Jersey.
Northeast Construction (Lakewood,
NJ) was responsible for a water pipe installation beneath the
Garden State Parkway near Bricktown, NJ. Soil conditions were
not ideal for auger use. The ground was primarily made up of
tightly packed, extremely fine sand.
Northeast Construction's Project
Manager George Gutierrez decided to contact a local machinery
company to inquire about the trenchless construction method
of pneumatic pipe ramming.
Gutierrez got in tough with a TT
Technologies distributor, looking for information about a pipe
ramming tool that could handle the installation of 100 feet
of 36-inch casing. Based on information from the distributor,
Gutierrez ordered a Grundoram Goliath Pipe Rammer.
Once the rammer arrived, tracks were
quickly laid to support and guide the rammer and the installation
of the first section of pipe was completed.
Welding crews than attached the second
section, and ramming was once again underway. The next two sections
of casing (20 feet each) were installed in less than an hour
each. The fourth section, however, took nearly two hours to
ram. Crews then decided to use their auger to remove spoils
in order to alleviate the internal friction against the pipe.
This would make the final casing installation faster and easier.
The final 20 foot section was installed
the next working day in just 38 minutes. The casing was installed
within one inch of grade.
The bottom line: Get the job done.
And get it done quickly, effectively and profitably. The contractors
in this story found a way to be successful, even in seemingly
overwhelming circumstances by combining tools.
Like the automobile, computer and
cellular phone, pipe ramming tools faced a great amount of scrutiny
upon their introduction. Now that contractors routinely combine
rammers and augers with positive results, the exception is fast
becoming the rule.
Pipeline & Utilities
Construction, September 1996, Pages 13-14, 16
|