|

In
order to successfully lift the Torrey Pine trees,
the Telliard construction crew created a lifting grid
for the Torrey pines
trees out of 15-foot long drill stems.
|
by Jim
Schill
Trenchless construction
methods are often the centerpieces of any construction project.
Sometimes, however, they can contribute to a project in
a small way and still have a big impact. Such was the case
recently for Telliard Construction, San Diego, CA, on a
project for the
city of San Diego, CA.
In an effort to relieve traffic congestion, the city of
San Diego decided to reconfigure a major intersection in
La Jolla (a suburb of San Diego).
The area is well known for the magnificent and rare Torrey
pine trees that tower above motorists from the intersections
island. In order to alleviate traffic congestion, the intersection
needed to be reconfigured and the Torrey pine trees moved.
City officials turned to Telliard Construction, San Diego,
CA. for a solution to the problem. According to Telliard
Construction Project Manager Dave Telliard, the city did
not intend to sacrifice the trees. He said, "The city
wanted the trees removed and relocated. Some could be re-planted
immediately, but some would have to wait until a new island
was constructed before they could be replanted. Upon accepting
the project, we became responsible for the trees for three
years."
Successfully removing and relocating the trees was a difficult
undertaking made easier through the use of trenchless technology,
specifically a Grundomat piercing tool from TT Technologies,
Aurora, IL.
|

Each
root ball was approximately 16 feet in diameter or
a radius of 8 feet from the trunk of the tree. The
root balls were
wrapped in landscape grade burlap and secured with
wire mesh.
|
Traffic
Solving
the traffic congestion problem in San Diego is one of the
top priorities of the citys mayor. According to the Texas Transportation
Institutes 2001 Urban Mobility Report, of the 68
cities evaluate in the report, San Diego received the fifth
worst travel rate index.
The project in La Jolla is a small part of San Diegos
effort to reduce traffic congestion. Telliard said, "The
two major roads that run through La Jolla merge at the island
intersection the city planned to reconfigure. Its
a major traffic zone and suffers from terrible congestion.
The island between the roads was home to seventeen rare
and protected Torrey pine trees. The city planned to create
a new intersection in order to alleviate some of the traffic
flow problems."
Not only was Telliard responsible for relocating the trees,
he was responsible for the their well being. Ensuring the
50-plus-year-old trees survival took great skill and know-how.
|

Before
utilizing the Grundomat piercing tool, the Telliard
crew place an average of one or two drill stems per
day. With the
piercing tool, Telliard was able to ram the stems
in place in approximately one to three minutes per
stem.
|
Arboriculture
Telliard Construction
has a good deal of experience handling and moving trees.
Telliard said, "I was fortunate to work on several
complex tree moving projects in the past. My father also
worked for some prominent hotels and moved palm trees, some
of which were the largest ever moved, at the time. We are
still primarily a general contractor, but we do have our
landscaping license and a good deal of that type of experience."
As part of the bid package, Telliard was required to hire
a consulting arborist for the project. The arborist provided
on-site consultation in terms of how the trees should be
removed, i.e. which roots to cut, how they should be cut
and how to contain them, and how the trees should be cared
for after they were moved.
Telliard said, "As I mentioned, were responsible
for the trees for three years. The arborists job was
to consult with us and report to the city. He tells them
how the trees are doing and, early in the project, evaluated
the trees chances of survival. He provides recommendations
for care of the trees as well."
Root Ball
As the Telliard
crew prepared to begin removing the trees, it became apparent
that the project was going to be more difficult than anticipated.
According to Telliard, the trees were planted very close
to the curb and gutter, and accessing enough of the trees
root systems to remove them successfully was going to be
a challenge.
Telliard said, "We needed to dig down and collect the
trees roots into a root ball. The root ball keeps
the tree alive while it is being moved. When the tree is
replanted, these roots grow back into the soil and the tree
continues to grow. Because of the curb and gutter issue,
we had to have the arborist on site, helping identify which
roots to cut. We had to be very careful during this process
and make sure we could get to enough roots for the trees
to survive."
Telliard and his crew chose to gather each trees roots
in a circular root ball. Each root ball measured 16 feet
in diameter, a radius of 8 feet from the trunk of each tree.
Telliard carefully dug around the tree, using a mini-excavator,
exposing the tree roots to a depth of approximately five
feet. Once the roots were exposed and cut, they were encased
in landscape-grade burlap and secured with a wire mess.
At this point, the root ball was complete and the trees
were then prepared for moving.
|

In
all, seventeen 50-year-old rare Torrey pine trees
were removed and relocated. The trees weighed between
70,000 and 100,000 lbs. and stood between 50 and 70
feet tall. A certified arborist consulted on the project.
|
The Plan
Removing
the 50- to 70-foot tall pine trees proved even more challenging
than preparing the root balls. Telliard, however, had a
plan. He created a grid composed of 4-inch diameter, 15-foot
long steel drill stems under the root ball. This allowed
a large crane to lift the trees and place them on a transport
vehicle. The problem arose in getting the drill stems in
place to form the lifting grid.
Telliard said, "We tried many different methods to
get the pipe through the ground and in place under the trees.
We tried pre-drilling. We tried pounding them in with a
Bobcat breaker. We tried a pneumatic hammer, but we just
werent getting the results we wanted until we talked
with Dennis Oellers from TT Technologies."
TT Technologies Product Specialist Dennis Oellers brought
several pneumatic piercing tools to the job site. Telliard
said, "Luckily I was able to get a hold of Dennis.
He came down with all his different tools and we tried to
figure out which one worked best. We went with the biggest,
baddest one he had." The tool Telliard selected was
the 7-inch diameter Grundomat-P 180.
Piercing
Tool
Telliard didnt
intend to use the piercing tool for boring; instead he wanted
to use it as a pipe rammer to drive the steel rods under
the trees. The results were amazing. Instead of taking all
day to pound one or two stems in place, it took a matter
of minutes.
Oellers said, "Each tree required up to 15 rods to
complete the grid. Between ten and 12 rods were rammed under
the root ball running north to south, spaced approximately
six inches apart. The last two were put in place manually,
one rod on the north end and one rod on the south end. The
final configuration appeared similar to a wooden raft. With
the Grundomat, we were able to get the steel pipes in place
in two or three minutes per stem."
Ramming the steel rods in place with the piercing tool was
a simple operation. The rods were placed at the base of
the root ball and the Grundomat secured to the end of a
rod with straps, similar to the ones used in pipe ramming.
Once the air was turned, ramming was under way. Telliard
said, "It was unbelievable. The tool performed like
no other. The amount of productivity we got from this tool
probably saved us a months worth of time and labor."
Remove, Relocate
& Replant
According to Telliard,
the crew worked in a two-week rotation. The crew spent two
weeks preparing a group of trees. Then came moving day and
the crew would move seven to eight trees at one time. A
300-ton crane was used to lift the trees, which Telliard
estimates weighed between 70,000 and 100,000 pounds each.
The trees were then placed on a lowboy trailer and relocated
until they could be replanted
Telliard said, "We tied the pipes that made up the
grid together, but when the crane lifted the trees the weight
alone was enough to keep everything in place. Before the
cranes got there we would go up on lifts above the canopy
of the tree and drop what we called messenger ropes to the
ground. When the crane came, we would attach the ropes to
the cranes straps and guide them through the tree
to keep them from breaking any branches."
Over a period of one month, all seventeen trees were successfully
removed. To date, eight of the seventeen trees have been
replanted. The remaining trees will be replanted upon completion
of a new island intersection. Telliard was very pleased
with the results of the project. He said, "We didnt
invent these methods for removing the trees, but we saw
so many ways to improve upon the techniques. Thats
why I was so glad to get a hold of Dennis at TT Technologies.
That just made it a great project."
|

In
order to get the drill stems in place, the Telliard
crew used a Grundomat P-180 piercing tool to ram the
drill stems under the root ball of each tree. Each
lifting grid was composed of twelve to fifteen drill
stems.
|
|