|
|

Crews
needed to weld the new HDPE coated steel gas main
together during pullback because there was not enough
space to stage the entire length of pipe. Note the
minimal excavation.
|
Any type of new
underground utility installation in Europe is highly scrutinized.
In many cases ancient streets, buildings and landscapes
face potential damage from conventional construction methods.
Needless to say, trenchless technology flourishes in Europe.
The recent expansion
of natural gas service by German gas provider Municipal
Works Lippstadt required the installation of two new gas
mains in the cities of Benninghausen and Heringhausen, Germany.
The new lines would serve both commercial and residential
customers in the area. Because the installations needed
to cross a local river, only trenchless installation was
considered. Directional drilling was chosen for what was
expected to be a routine drilling project. By the time the
project was complete, however, it took added percussive
power and rock drilling equipment to successfully cross
the river.
Job
Site Layout
The utility provider planned to pull in two, 6-inch
HDPE pipes together with the new gas main in a three-pipe
bundle. One would be used as a spare potable water line,
the other as an accommodation pipe to be leased at some
time in the future. To complete the installations, Municipal
Works Lippstadt turned to trenchless equipment manufacturer
Tracto-Technik, Lennestadt, Germany (known as TT Technologies
in North America).
Because of numerous
sub-utilities at the Herringhausen site, as well as a sheet
piling on the riverside, determining the proper bore path
was critical. Both river crossings would be approximately
395 feet in length. Several types of steel pipe were evaluated
based on the minimal bending radius. A maximum cover of
23 feet was determined and a special HDPE coated 10.5-inch
diameter steel gas pipe was chosen for the project.
Because local
soil conditions were already well known from a crossing
successfully completed in the past, the Municipal Works
crew did not expected any soil problems with the project.
The sand/clay soils were expected to remain consistent throughout
each bore. Soil investigation at deeper levels was deemed
unnecessary.
Drilling at the
Herringhausen site began in August with a Grundodrill
20S from
Tracto-Technik.
|

The
Grundodrill
20S incorporates percussive action with
hydraulic thrust and rotational torque. The percussive
actions allows the drill to steer through difficult
soil conditions.
|
Percussive
Drilling
Standard directional drills use hydraulic thrust and
rotational torque to complete their pilot bores. With the
addition of water/bentonite slurry most small- to mid-range
drills operate adequately in moderate soil conditions. But
as soon as densely compacted or rocky soils are encountered,
these drills reach their thrust force, rotational torque
and flushing pressure capacities and cannot complete the
bore. The same is true during extremely long bores.
The Grundodrill is
a combination hydraulic/percussive steerable drilling
system. According to TT Technologies' President Chris
Brahler, directional drills with percussion are relatively
new to North America and promise to have a large
impact on directional drilling industry here, like
they have in Europe.
Brahler
said, "Often
contractors look to larger, more expensive and less practical
directional drill rigs to get more hydraulic thrust force
when they encounter difficult situations. By adding percussion
to the drilling process, the hydraulic/percussive drill
is able to steer the drill head in soil conditions where
standard, comparably sized drill rigs cannot."
The percussive
force is created by impacting the drill stem at the drill
rig. This provides the dynamic energy needed to steer in
difficult and rocky soils. The percussive impacts on the
highly flexible drill stems can be adjusted at a rate up
to 1,000 impacts per minute.
The
Bore
After a good start, progress slowed greatly at 100 feet
into the bore at a depth of 16 feet. An obstacle, possibly
a large boulder, seemed to be the reason. But this could
not be confirmed. The percussive hammer was operating at
full capacity and was able to keep the bore progressing.
After a while it became evident that the crew was dealing
with more than just rocky soil. They were unable to get
past the obstacle and eventually there was hardly any detectable
thrust.
A
solid rock formation was now suspected, which could
not be penetrated without rock drilling equipment. The
percussive action of the drill had advanced the bore
to a favorable point to start rock drilling operations.
The Grundodrill was
quickly re-equipped with rock drilling equipment and the
pilot bore resumed without further problems. The large
rock formation the crew encountered continued over the
next 300 feet.
A substantial
amount of drilling fluid was used for the rock drilling
operation. For this project approximately 5.5 tons of boring
fluid was used. The drilling fluid was properly disposed
of with some used as fertilizer on the surrounding farm
fields.
|

Two
6-inch HDPE pipes were pulled back along with the
new 10.5-inch steel gas main in a 3 pipe bundle. The
20-inch backreamer was specially designed for this
project.
|
The Pullback
In
order to accommodate the collective diameter of the three
pipes, special steel chisel backreamers were used to expand
the pilot bore. The first backreamer was 8 inches in diameter.
After successfully backreaming to 8 inches, the second,
12-inch backreamer was used. The third backreamer was 20
inches in diameter. The large diameter backreamer was specifically
made for this particular project. All three pipes were pulled
in together in one bundle, while attached to the 20-inch
backreamer.
Thanks to good
prep work, pullback was completed in less than three and
half hours, including a 45 minute delay for welding on the
second pipe string. Welding the pipe during operations was
necessary because there was not enough space to totally
lay out the pipe length completely at the beginning of the
project.
After the pullback
was complete, the new gas line was successfully pressure
tested and readied for service. Everyone was very satisfied
with the results of the project, especially considering
the unexpected encounter with the large rock formation.
In Benninghausen,
approximately one and a half miles away from the Herringhausen
job site, the second crossing was complete. No problems
were encountered during the pilot bore on the second crossing.
Crews at the Benninghausen site used a smaller Grundodrill
10S. No rock drilling equipment was required.
Pipeline & Gas Journal,
May 2001
|