
McDonald Plumbing choose lateral
pipe bursting for the lateral replacement project at the
Radisson Hotel in Grand Rapids, MI. Minimal disruption to
the hotel and guests was key to this project.
|
Replace 100 feet of deteriorated 3-inch cast
iron sewer later
with minimal disruption at a Radisson Hotel- Grand
Rapids, MI
Contractor:
McDonald Plumbing Grand Rapids,
MI
Customer:
Radisson Hotel- Grand Rapids, MI
Equipment:
Grundotugger Lateral Pipe Bursting
System w. Fusion Equipment & Hydraulic
Power Pack, TT Technologies, Aurora, Ill
Major renovations don’t necessarily mean major disruption.
That was the case recently for a Radisson Hotel in Grand Rapids,
MI. Major renovation and upgrade work was being done to the public
areas of the hotel including the swimming pool and restaurant.
As part of the project, the hotel’s sanitary sewer lines
were also evaluated. Experienced utility contractor McDonald Plumbing,
Grand Rapids, MI was contracted to televise the lines within the
restoration area, and provided rehab or replacement services if
necessary.
According to McDonald Plumbing Vice
President Scott McDonald the lines were in fairly poor condition.
He said, “The drains
were cast iron and the bottoms were completely corroded away. They
needed to be replaced. The normal course of action would have been
to saw cut open the floor and hand dig the entire sewer lateral
and replace it. But we wanted to find a less time consuming and
more economical solution.”

A Grundotugger lateral pipe
bursting system was used on the project. Only small launch
and exit pits are needed to utilize the trenchless pipe
bursting system.
|
Open cutting the floor would have meant a tremendous amount of
restoration. The area would need to be re-concreted and the floor
cover would need to be replaced. This would not only add cost to
the project it would add a significant amount of time as well.
McDonald looked at several options before talking with pipe bursting
specialist Scott Redman with trenchless equipment manufacturer
TT Technologies, Aurora, Ill.
McDonald said, “A portion of the
line ran under a large section of decorative concrete. The restoration
of that concrete alone would have easily doubled the cost of
the project. Plus, all digging in the hotel had to be done by
hand. It would have been a large undertaking to dig up that entire
section of pipe by hand. We had been looking at trenchless bursting
equipment for quite some time and this was an opportunity for
us to really put the equipment to the test.”
Redman said, “While every lateral replacement situation
poses its own unique challenges, a trenchless rehab option is almost
always preferable. However, many trenchless options are not applicable
to lateral replacement. Pipe
bursting offers a viable solution
for lateral replacement. Even though the area for this particular
project was undergoing restoration, digging up the floor and the
concrete areas was not necessary. Trenchless pipe bursting was
definitely the right method for this particular project.” McDonald
and his crew used a Grundotugger lateral pipe bursting system from
TT Technologies.
Lateral Bursting

McDonald Plumbing Vice President
Scott McDonald estimated that restoration alone would
have double the cost of the project if completed by
conventional hand digging. Through lateral bursting
the crew was able to complete the project quickly with
only minor restoration costs.
|
Pipe bursting is well suited
for lateral replacement. It is capable of replacing relatively
small diameter pipe and allows for increase or upsize of the original
host pipe diameter. That fact alone is extremely valuable on jobs
where lines are being replaced because of capacity issues.
Redman noted that improvements in lateral
bursting equipment have made the method accessible to everyone
from specialty to general contractors. Redman said, “The new lateral bursting equipment
is very portable, but doesn’t compromise on power. It’s
also easy to use. Both static and pneumatic lateral bursting systems
can be easily transported in most pick-up trucks. They only require
a minimal crew compliment to operate. And they really get the job
done well. With the big push for lateral replacement, the timing
of some of this equipment couldn’t be better.”
On the Job
The McDonald crew prepared to replace
the 100 feet of 3-inch diameter cast iron lateral by digging launch
and receiving pits.
A small launch pit measuring 5 feet by 5 feet
was dug inside the hotel at the end of a hallway. A slightly larger
receiving pit was dug outside of the building. The crew rodded
the existing line
and pulled back the winch cable for the Grundotugger
that was positioned in
the receiving pit. At the launch pit, a
standard direct bolt expander was connected to the first
section
of 4-inch HDPE.
According to Redman there are several
types of methods used for connecting an expander to HDPE. He
said, “The direct bolt
method is very common in main line bursting, but can also be used
for lateral bursting. For difficult lateral projects, a pneumatic
piercing tool can be used to assist bursting operations from the
inside of the new HDPE, behind a direct bolt expander. A quick
grip type expander connection is also common in lateral bursting,
but does not allow the piercing tool assist option.” After
the expander was in place, the winch line was connected.
The crew
then connected the hydraulic power pack to the bursting unit. According
to Redman the hydraulic system is a very important part of a static
pipe bursting system. He said, “A proper
hydraulic system can mean the difference between success and failure
in the field. The system needs to be capable of handling foreign
material and other contaminants found at every jobsite. Plus the
hydraulic power pack needs to produce enough horsepower to meet
the challenges of bursting. An electro-hydraulic system is the
best option for hydraulic power. A simple industrial hydraulic
system with a sequence valve design doesn’t survive long
in the field.”

Because of limited space, the
crew fused 10-ft sections of 4-inch HDPE while bursting.
Ultimately 100 feet of the existing 3-inch cast iron
lateral was replaced with 4-inch HDPE.
|
After all of the connections were made, bursting
operations began with the bursting unit steadily pulling the new
pipe through the existing line. As a section of pipe was installed,
another section of pipe was fused on. Because the launch pit was
located inside of the hotel within close proximity to the front
desk, space was limited and the McDonald crew needed to fuse the
new pipe together in 10-foot sections while bursting.
Within an
hour the new HDPE was in place with minimal disruption to the hotel
hallway. The McDonald crew tied-in the new HDPE and made the hotel
connection. After the new lateral was tied into the system, crews
set to work restoring the launch and receiving pits.
Reaction
According to McDonald the hotel project
supervisor was very pleased with the results of the bursting project.
In addition, McDonald said he and his company have several lateral
bursting jobs lined up and have since successfully completed several
difficult lateral bursting projects.
He
said, “”We've had a couple of projects now that
I’m not sure how we would have approached them without the
bursting system. It's been a very good investment and expansion
of our service."”
Cleaner , June 2006
|