|
by Jim Schill

The Herscher storage field expansion project included
the replacement and upgrading of a 2,300-foot, 6-inch
fiberglass water line to an 8-inch SDR 11 HDPE line
through pipe bursting. That particular line distributes
water to and from water pump wells and water disposal
wells. Pictured staged 8-inch HDPE. |
While big trenchless pipeline installation
projects often receive the majority of the attention in
the natural gas industry, sometimes smaller trenchless
projects play an important role in maintaining the flow
and storage of natural gas and deserve their due. A recent
project for [Kinder Morgan] Natural Gas Pipeline Company
of America’s
natural gas storage facility in Herscher, Ill. is a good
example.
The Herscher natural gas storage facility
was once part of the Trenton Oil Fields, which began operating
in the 1880s, but was abandoned in the early 1900s. Since
being abandoned, the Herscher site has been used to store
natural gas beginning in the 1950s, with Cambrian-age sandstone
providing an ideal formation for the underground storage
of natural gas.
The American Gas Association (AGA)
reports that there are approximately 420 operating natural
gas storage field in the US. For an average winter
heating season, approximately five months, about 15 to
20 percent of natural gas consumed originates in an underground
storage facility. These
underground storage facilities are commonly depleted gas
reservoirs, aquifers, mined or salt solution caverns, or
depleted oil reservoirs, like the field in Herscher, Illinois.
According to the Federal Energy Regulatory
Commission (Docket No. CP08-032-000), Natural Gas Pipeline
Company of America filed for approval of an expansion of
the Herscher field in January of 2008. The ultimate goal
of the project was to increase the field's capacity by
10 billion cubic feet, and increase the peak day withdrawal
capacity. The expansion would include, new water withdrawal
wells, new and extended water disposal wells, new water
pipelines, one new compressor station addition, and extension
of five existing natural gas injection/withdrawal wells. In
addition, the project included upgrading and repairing
portions of the existing storage system.
Project
approval was granted in the summer of 2008 and HOSS Construction
Co., Searcy, Ark., was contracted to complete the work. According
to HOSS Construction general manager and vice president,
Dave Seitz, his company is a utility and mechanical contractor
serving the pipeline, communications and municipal industries,
specializing in directional drilling. The Herscher
storage field project gave Seitz the opportunity to expand
the company’s
capabilities into static pipe bursting for the replacement
of a 6-inch fiberglass water line.
Seitz said, “Due
to the time of year, the well-maintained right-of-way,
business activity and the concern for ensuring that the
business for adjacent landowners and property appearance
was maintained, the decision came down to directional drilling,
or pipe bursting the segment. Pipe bursting, in this
situation, required only the excavation of one tie-in connection hole utilizing
only one path of ingress and egress. Considering all costs, boring, and clean-up,
versus one tie-in hole, pipe bursting was selected.” For the project,
Seitz enlisted the assistance of trenchless equipment manufacturer TT Technologies,
Aurora, Ill. and the 800G Grundoburst static pipe bursting system.

During the static bursting process specially designed
bladed rollers are pulled through an existing pipe.
As the bladed rollers are pulled through, they split
the host pipe and expander attached forces the fragmented
pipe into the surrounding soil while simultaneously
pulling in the new pipe. Pictured tri-blade cutter,
expander and new HDPE. |
Contractor & Project Background
While a
relatively new company on the books, HOSS Construction
has years of utility and pipeline contracting experience. Seitz,
a civil engineer, began his career with NGPL at the Herscher
Storage field almost 30 years ago. After 20 years
with NGPL, Seitz spent several years as a partner in a
pipeline and utility construction firm and a consultant
in the pipeline industry before finally striking out on
his own and starting HOSS construction in 2005. While
the project at the Herscher storage facility may have felt
like familiar territory, it was also an opportunity for
Seitz to explore a trenchless pipe rehabilitation and replacement
method that was new to HOSS Construction, static pipe bursting.
The project took place along the south side of Illinois
State Highway 115 on the east side of the town, and involved
the replacement and upgrading of a 6-inch fiberglass water
line to an 8-inch SDR 11 HDPE line. That particular line
distributes water to and from water pump wells and water
disposal wells.
Water pumped
from the ground during withdrawal season has a slightly
elevated salt content that the water absorbs naturally
underground. According to TT Technologies
Pipe Bursting Specialist Bryan Bachmann, this may have
contributed to the demise of previous pipes, like cast
and ductile iron waterlines. This fiberglass line,
however, was simply being replaced for capacity reasons
because of the overall expansion.
The line was installed between an existing 10-inch steel water line and a 6-inch
PVC municipal supply water main. The area was located in the state highway right-of-way
on the back slope of a drainage ditch. The area was well maintained by adjacent
business owners and four existing driveways were used for business ingress and
egress. The total length of the segment was approximately 2,300 feet.

The crews divided the run into two segments, position
the bursting unit in the middle. While bursting the
first run, crews allowed the Quicklock bursting rods
to pass through the machine and rod the second bursting
run, a time saving technique. |
Static Pipe
Bursting
According to Bachmann, static
pipe bursting has established itself as a dependable
trenchless pipe replacement method throughout the U.S.
He said, “Static pipe bursting
has really come to the forefront of trenchless pipe rehab
and replacement. A lot has to do with the fact that the
method has really gained acceptance from the utility construction
industry and the fact the method itself has grown in terms
of its versatility.”
The static bursting process is simple, yet effective.
Specially designed bladed rollers are pulled through an
existing line by a hydraulically powered bursting unit.
As the bladed rollers are pulled through, they split the
host pipe. An expander attached to the rollers forces the
fragmented pipe into the surrounding soil while simultaneously
pulling in the new pipe.
Patented Quicklock bursting
rods are linked not screwed together like traditional
drill stems or other static systems. This system speeds
the installation process as well as the breakdown procedure.
The rods can be quickly removed one at a time at the
exit pit as bursting is in operation. While
HDPE is commonly used, new techniques and technologies
are allowing contractors a choice when it comes to product
pipe. According to Bachmann, other pipe materials are being
installed now through static bursting include ductile iron,
PVC, specially designed clay and steel.
He said, “Several techniques have been developed by TT Technologies and
partner contractors to allow the use of a variety of product pipe options with
the static pipe bursting process. Beside its inherent trenchless aspect,
this is one of the main reasons that the popularity of the method has really
taken off. Often HDPE is the right choice for a project. However,
for certain municipalities or parts of the country it’s ductile iron, PVC,
or clay. It really provides a level of choice and versatility previously
not available with the bursting process. The reception
by contractors, engineers, and municipalities has been
tremendous, and has led to the continuing growth of the
method, as well as continuing innovation from the field.”
On the Job
The pipe bursting project was
to be completed in just two pulls. The first segment was 1,275 feet and the
second was 1,025 feet. A Grundoburst 800G static
bursting system with a tri-blade cutter was chosen for
the project. HOSS crews excavated a single machine
pit in the middle of the two bursting runs. The pit
measured 4 feet wide by 5 feet deep by 16 feet long. Once
the pit was dug, crews lowered the bursting unit into the
hole and prepared the support and bracing.
Seitz said proper bracing is
important to the success of the bursting operation. He said, “The
biggest challenge was supporting the machine given the
round conditions. The soil was a 24-inch top layer of
good Illinois black dirt, and below the black dirt was
a clay-loam with pea gravel. The soil had high moisture
content and the water level was just at the bottom of
the 5.5-foot excavation. Additional support structures
and equipment were required to hold the machine during
the pullback. The Grundoburst unit had enough power to
do the job and the design of the unit enable us to maneuver
and add additional support and bracing during the pull-back
process.”
Crews rodded the first 1,275-foot
section of pipe. At
the launch pit, crews then connected the tri-blade bursting
head and then bolted the expander with the new fused 8-inch
HDPE to the bursting rods. The first 750-foot segment
of pipe was pulled in with only one stop for a fusion joint
adding 600 feet in the staging area. While the bursting
of the first run was in progress, crews allowed the locked
bursting rods to pass through the machine and rod the second
bursting run. Bachmann said, “This is a huge
time saving method, unique to Quicklock style bursting
rod systems. You’re essentially accomplishing
two tasks at once. It’s really contributes
to productivity and efficiency.”
Once the first run was complete
crews took the Grundoburst, rotated it 180 degrees in
the machine pit in order to pull from the other direction. Crews then completed set-up
for the second burst attaching the tri-blade bursting head,
expander and new 8-inch HDPE. The second 1,025-foot
segment was also successfully pulled into place and all
the connections were made without incident.
Bachmann said, “The project went really well and that can be directly attributed
to the quality people at HOSS Construction. They’re great to work
with and excellent in the field.” In addition to the static bursting
portion, HOSS Construction also completed the additional portions of the Herscher
field expansion project. Seitz said that he intends
to add static pipe bursting to his list trenchless services
and looks forward to utilizing the method again in the
future.
Pipeline
& Gas Journal,
May 2009 |